LNG Long Sơn power projectDự án điện khí LNG Long Sơn
A 1,500 MW LNG plant on the coast. Investment policy approved in March 2026; no investor selected in VIRO’s evidence, and commercial operation is targeted for June 2031.
Readiness ladder · Thang sẵn sàng
Why this stage
Decision 1702/QĐ-UBND of 24 March 2026 approved the investment policy, with the investor to be chosen by competitive tender.
Fact 24 Mar 2026 · Báo Đấu thầu
Next rung — Investor / contractor selected: A delivery party is selected; construction not yet observed.
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Milestones · Mốc kế hoạch và thực tế
Planned against achieved
| Milestone | Planned / target | Achieved | Status | Source |
|---|---|---|---|---|
| Investment policy approved | — | 24 Mar 2026 | Achieved | Báo Đấu thầu |
| Investor selected | Jun 2026 | — | Unknown | Báo Đấu thầu |
| Commercial operation | Jun 2031 | — | Pending | Báo Đấu thầu |
Evidence · Bằng chứng
What the record shows
- Target3 Apr 2026The planned sequence was to finish investor selection by June 2026, complete the feasibility study and negotiate the power price and PPA from mid-2026 to mid-2027, arrange finance, clear the site and select an EPC contractor in 2027–2028, and build in 2028–2031. VIRO found no report that an investor has been selected.
- Reported3 Apr 2026Reported obstacles for LNG power generally: the electricity-price mechanism and minimum contracted output in the PPA, raising debt as international lenders grow cautious on fossil projects, and LNG price and exchange-rate volatility. Of 15 LNG plants planned to operate in 2025–2030, only Nhơn Trạch 3 and 4 were complete at the time of reporting.
- Fact24 Mar 2026Decision 1702/QĐ-UBND of 24 March 2026 approved the investment policy: about 1,500 MW, preliminary investment of VND 39,867 billion (about US$1.6 billion) at 20% equity and 80% debt, a 50-year operating period and a target of commercial operation in June 2031.
- Fact24 Mar 2026The 42.56 ha site includes 12 ha of protective forest land. The investment-policy decision states that if the project cannot meet the conditions for converting forest land, the competent authority may consider terminating it.
Unknown · Chưa rõ
- Whether an investor has been selected.
- Power purchase agreement and electricity price.
- Forest-land conversion.
- Construction start.
VIRO analysis
The coastal energy corridor in the draft plan depends on projects like this moving from an approved policy to a signed power contract and a selected investor.
Sources · Nguồn
- LNG Long Sơn power project: challenges to resolve — Báo Đấu thầu, 3 Apr 2026