HCMC–Thủ Dầu Một–Chơn Thành ExpresswayCao tốc TP.HCM – Thủ Dầu Một – Chơn Thành

The industrial spine through Bình Dương’s factory belt. Under construction since February 2025; no completion date in VIRO’s evidence.

4/7 · Under construction · Đang thi côngLast observed 31 Oct 20261 sources
Readiness ladder · Thang sẵn sàng
Why this stage

The Prime Minister ordered construction to start on 1 February 2025; by July 2026 compensation and site clearance were still being completed.

Reported  10 Jul 2026 · Báo Đầu tư

Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.

Schematic map of Southern Vietnam infrastructure projects by readiness stageApproximate positions of tracked projects in and around Ho Chi Minh City, coloured by observed delivery stage. Not for navigation.ĐỒNG NAITÂY NINHĐỒNG THÁPHỒ CHÍ MINH CITYEast SeaThủ Thiêm–Long Thành Railway — In planHCMC Ring Road 3 — Under constructionHCMC Ring Road 4 — Under constructionMetro Line 2 (Bến Thành–Tham Lương) — Under constructionHCMC–Mộc Bài Expressway — Under constructionHCMC–Thủ Dầu Một–Chơn Thành Expressway — Under constructionBiên Hòa–Vũng Tàu Expressway — Partly operationalBến Lức–Long Thành Expressway — OperationalHCMC–Long Thành–Dầu Giây Expressway (widening) — OperationalMetro Line 1 (Bến Thành–Suối Tiên) — OperationalHCMC coreThủ ĐứcBiên HòaThủ Dầu MộtBàu BàngPhú MỹVũng TàuBến LứcHiệp PhướcCủ ChiLong Thành International Airport (phase 1) — Under constructionCái Mép–Thị Vải deep-water port cluster — Usable for businessCần Giờ International Transshipment Port — Investor / contractor selectedNhơn Trạch 3 & 4 LNG power plants — OperationalHCMC Free Trade Zone (Cái Mép Hạ) — ApprovedVietnam International Financial Centre (HCMC) — OperationalDirect power purchase (DPPA) rules — ApprovedLNG Long Sơn power project — Approved
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Schematic, approximate geometry for orientation — not navigation or project alignments. Pole circles follow the structure of the HCMC master plan; they are not official boundaries. Observation run 31 Oct 2026.
Milestones · Mốc kế hoạch và thực tế

Planned against achieved

MilestonePlanned / targetAchievedStatusSource
Construction start ordered—1 Feb 2025AchievedBáo Đầu tư
Clean-site handoverQ3 2026—UnknownBáo Đầu tư
Completion——UnknownBáo Đầu tư
Evidence · Bằng chứng

What the record shows

  • Reported
    10 Jul 2026
    A national key transport project. The Prime Minister ordered construction to start on 1 February 2025 and required early completion. Land recovery covers more than 327.2 ha and affects 1,613 households, individuals and organisations, with VND 8,283.2 billion budgeted for clearance.
  • Reported
    10 Jul 2026
    HCMC reported that some cases still lacked an approved compensation plan, had not taken compensation or had not handed over land, which it called a risk to the schedule, and made clearance an urgent task for Q3 2026. The report gives no completion date.
Unknown · Chưa rõ
  • Share of site handed over.
  • Section-by-section opening dates.
  • Completion and operation dates.
  • Total length and contract form.
VIRO analysis

It would give the northern industry pole a dedicated expressway to the city and the ring roads.